Site plan approval pending; county commission vote tabled to November 17, 2026.
Project Camellia
Effingham County, Georgia
OpenAI
Civil, power, water, GC/CM and early site infrastructure
Track major U.S. data center developments, known construction teams, project milestones, and contractor next steps—all in one free tracker.
25 tracked projects. 27 source records. November 2026 edition.
Preview 10 projects firstEvery project in the DCCR Opportunity Tracker is evaluated for construction timing, procurement activity, known contractors and remaining opportunity.
All 25 projects are Partially Verified; that means some project information has been checked, not that every detail is confirmed. Each project was last verified November 12, 2026. Procurement status is Unknown for all 25, and no current open construction solicitation has been verified. The 19 displayed scores are historical assessments, not November 2026 opportunity scores; six projects remain Unscored. DCCR tracking status is an editorial posture, not evidence of open bidding.
DCCR scores on retained projects are historical research assessments, not verified November bidding scores. New projects are Unscored.
Site plan approval pending; county commission vote tabled to November 17, 2026.
Effingham County, Georgia
OpenAI
Civil, power, water, GC/CM and early site infrastructure
Proposed campus; land not acquired and project approval pending as of October 2026.
Near Danville, Montgomery County, Missouri
Amazon
Not established by the supplied reporting; no contractor or procurement path identified.
Proposed redevelopment; approvals and utility studies remain to be confirmed.
Alton, Illinois
TerraWatt
Not established from the project website; no contractor or procurement path identified.
Get free access to the full tracker, including project details, construction intelligence, source links, and contractor next steps.
TDLR registered; projected construction start March 1, 2027 and completion December 14, 2028; filing dates do not confirm active construction.
1130 E. Belt Line Rd, Lancaster, Dallas County, Texas 75146
SI DFW02CAMPUS LLC (TDLR-listed owner)
No contractor team or solicitation verified; the TDLR filing supports project size and projected dates only.
Initial DRI information filed; Request for Comments Made. Regional review ongoing; construction approval not established.
Floyd County, Georgia
Microsoft Corporation
No construction team or procurement opportunity established by the DRI filing.
Auxiliary water building is registered in the TDLR system; scheduled construction dates are preliminary filing data.
Westlake, Texas
PowerHouse Data Centers
Not established by the auxiliary-building filing; no GC/CM or solicitation documented.
Proposed project; second-reading approval of the development agreement November 3, 2026; final approval pending.
389 Tyger River Industrial Drive, Moore, South Carolina
AIB CLT1 LLC (development agreement party)
No contractor or procurement opportunity established; no solicitation documented.
VWP coverage application in progress; approval not recorded.
Prince William County, Virginia
Microsoft
No contractor or solicitation documented; the VWP coverage application remains in progress.
Nscale reports construction underway; Phase One target is early 2028.
Mason County, West Virginia
Nscale
No GC, trade award or open solicitation is identified in the developer announcement.
TDLR registered; start projected for January 4, 2027.
Irving, Texas
CoreSite
No GC/CM or solicitation is identified by the TDLR registration.
Investment, MW, acreage and building information when available.
Known developers, GCs, CMs, engineering firms and major partners.
Editorial tracking posture is separate from a documented solicitation status.
A 0–100 editorial score based on remaining opportunity and procurement timing.
Clearly distinguish verified facts, relationship signals and unresolved information.
The specific contractor action DCCR believes is worth investigating next.
Supported by reliable project, company or public documentation.
Evidence of project involvement or a relationship, but not enough to claim a specific contract award.
Important contractor, package or procurement information has not yet been publicly verified.
Prequalification is a route. It is not an open bid.
Follow U.S. data center projects, monitor construction milestones, and identify documented contractor relationships before your next outreach.